6718 Residence Update 3

RDM Architecture / Perspective  / 6718 Residence Update 3

6718 Residence Update 3

With the pool issue resolved, Hurst Construction has taken advantage of the unseasonably warm weather to pour the foundations and start the framing.

The screened porch foundation is sitting on a pool full of concrete.  

The retaining walls on the south side of the house create a lawn that will help replace some of the backyard that will be taken up with the new screened porch and patio.